Tramway Track Upgrade at Prince Volodymyr the Great Avenue

The second phase of the tramway track repair has commenced at the intersection of Prince Volodymyr the Great Avenue and Academician Zabolotny Street.

The first phase of the renovation, which took place from May 16 to June 2, was successfully completed, covering 50 meters of the straight section.

Currently, the second phase has started, which involves repairing an additional 100 meters of the tramway track, running from June 3 to June 26. Following this, two more phases are planned, including a major overhaul with partial replacement of the curved section.

The total length of the repair area is 250 meters. The work is being carried out in stages with partial traffic restrictions.